M
Matt
Hello all,
I'm fairly new to project and am ammending a project already created by
someone else, my specific problem is that i don't want some of my tasks to be
split over the none working part of the day. Basically all my task are
between 15mins and 4hours each and my working days are 8hours long. My
problem is that my 4hour tasks have to be completed in one go, therefore I
don't want project to start the 4hour task on a day if they can not be
completed that day.
If someone knows if/how i can overcome this problem it would be much
appreciated.
I am using Project Standard 2003
Regards
Matt
I'm fairly new to project and am ammending a project already created by
someone else, my specific problem is that i don't want some of my tasks to be
split over the none working part of the day. Basically all my task are
between 15mins and 4hours each and my working days are 8hours long. My
problem is that my 4hour tasks have to be completed in one go, therefore I
don't want project to start the 4hour task on a day if they can not be
completed that day.
If someone knows if/how i can overcome this problem it would be much
appreciated.
I am using Project Standard 2003
Regards
Matt