Tasks are not displayed in the same order as in the project

K

Kathleen

The project plan is listed by phase with subtasks assigned to team members.
The order would be : Inception, Elaboration, Construction.

The team members tasks display in alphabetical order:
Construction, Elaboration and Inception

How can I filter the tasks so that they mirror exactly what is displayed on
the project managers plan.

Thanks,

Kathleen
 
K

Kathleen

Julies,

The view is; "View my tasks" with the filters of "Show summary tasks & Show
"to do lists" as (checked)

Kathleen
 
J

JulieS

Hi Kathleen,

Thanks. I assume you are referring to a view in Project Web Access, not
directly through Microsoft Project. I'm afraid I haven't worked extensively
with server and can't help much further.

Although several of the regular responders here do use server, you may get a
quicker answer by posting your question to the Project Server NG.

Julie
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top