S
Stephen Nulty
I have a serieso ft unrelated tasks in a Project. For each
of them I want to specify a Start Date, a Finish Date and
a Duration. I do not want Project to do any auto
calculation of any of these values, I need them to remain
exacrly as entered. However, when I modify the start or
end date, the duration is automatically updated.
How can I stop this auto modification from taking place
Regards
Steve
of them I want to specify a Start Date, a Finish Date and
a Duration. I do not want Project to do any auto
calculation of any of these values, I need them to remain
exacrly as entered. However, when I modify the start or
end date, the duration is automatically updated.
How can I stop this auto modification from taking place
Regards
Steve