S
Steve D
I am trying to do something quite simple, but am being twarted by the power
of MS Project.
I have a number of tasks that have a duration of a number of months, but the
work involved woulud only be a few days. I cannot work out how to enter this
infromation in project for example:
A task will start on 1st May 2006 and finish on 30th July 2006, but the
actual work involved will only be 5 days. I wanto to display the work done as
a percentage of the whole task on the Gannt chart.
I have tried to use work and contraints, but as I cannot have more than 1
constrint on a task, when I change the work the start an finish dates change,
and I want these to remaion fixed.
Can anyone help ?
of MS Project.
I have a number of tasks that have a duration of a number of months, but the
work involved woulud only be a few days. I cannot work out how to enter this
infromation in project for example:
A task will start on 1st May 2006 and finish on 30th July 2006, but the
actual work involved will only be 5 days. I wanto to display the work done as
a percentage of the whole task on the Gannt chart.
I have tried to use work and contraints, but as I cannot have more than 1
constrint on a task, when I change the work the start an finish dates change,
and I want these to remaion fixed.
Can anyone help ?