M
Merlin
Hello everybody,
I am new to MS-Project. Is there a way to shift the whole project in
time? I am planing a huge IT project but the start date is not fixed
yet. So if I plan everything now and the start date will shift for a few
weeks, do I have to touch every single task to set the correct start
date or is there a functionality to do that?
Thank you for any help.
Best regards,
Merlin
I am new to MS-Project. Is there a way to shift the whole project in
time? I am planing a huge IT project but the start date is not fixed
yet. So if I plan everything now and the start date will shift for a few
weeks, do I have to touch every single task to set the correct start
date or is there a functionality to do that?
Thank you for any help.
Best regards,
Merlin