Timeshifting the project

M

Merlin

Hello everybody,

I am new to MS-Project. Is there a way to shift the whole project in
time? I am planing a huge IT project but the start date is not fixed
yet. So if I plan everything now and the start date will shift for a few
weeks, do I have to touch every single task to set the correct start
date or is there a functionality to do that?

Thank you for any help.

Best regards,

Merlin
 
J

Jan De Messemaeker

Hi,

1. If your plan does not contain any constraints, just change the Project
Start date in Project, Project Information.
2. If it does, show the Analysis toolbar (Through Tools, customize,
toolbars) and click adjust dates.
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 