to show actual % of work completed

M

ML

Hi,

I like to show the actual % of work completed in the Gantt Chart which is
independent to the start and finish dates.
e.g. jason has a task 80% done on Feb 22, 2005 and the due date of this
task is March 31, 2005. How can I show the actual % of work completed in
this case.

Thanks,
ML
 
P

Project Slave

Insert a new column in the Gantt Chart View (>insert>column) and select '%
work completed"
 
J

JulieS

Hi ML,

I'm not sure from your post if you want to show the % work complete in the
task sheet (in which case follow "Project Slaves" direction) or as text next
to the bar in the Gantt chart. To show % Work Complete next to the bar,
choose Format> Bar Styles. Find the bar for the task type (Normal, Critical
etc.). At the bottom of the Format Bar Styles dialog box, click the Text
tab, select where you want the text to appear (Left, Right etc.) and select %
Work Complete from the field list.

Hope this helps. Let us know how you get along.

Julie
 