Hi,
I like to show the actual % of work completed in the Gantt Chart which is
independent to the start and finish dates.
e.g. jason has a task 80% done on Feb 22, 2005 and the due date of this
task is March 31, 2005. How can I show the actual % of work completed in
this case.
Thanks,
ML
I like to show the actual % of work completed in the Gantt Chart which is
independent to the start and finish dates.
e.g. jason has a task 80% done on Feb 22, 2005 and the due date of this
task is March 31, 2005. How can I show the actual % of work completed in
this case.
Thanks,
ML