I
Itai Raz
Hi,
I'm sure there must be something I'm missing here.
I could never find a way to present "total work" for a project that
does not have resources assigned to its tasks.
Seems like something trivial - you start a project, you list all the
tasks and their durations, and then you want to see the overall work
which will be required for this project in man days/weeks/months/hours
(in order to decide, for instance, how many resources to assign to this
project). One way I found was to assign a dummy resource to all tasks
and then look at the total work or simply use leveling so that the
project spreads out sequentially. This is stupid, though - having to go
over every task in the project assigning a dummy resource to it. Not to
mention the fact that I have to make sure I skip all summary tasks on
the way, otherwise I get discrepancies.
Isn't there a report that just summarizes the amount of work involved
in the project, regardless of resources?
Thanks,
--itai
I'm sure there must be something I'm missing here.
I could never find a way to present "total work" for a project that
does not have resources assigned to its tasks.
Seems like something trivial - you start a project, you list all the
tasks and their durations, and then you want to see the overall work
which will be required for this project in man days/weeks/months/hours
(in order to decide, for instance, how many resources to assign to this
project). One way I found was to assign a dummy resource to all tasks
and then look at the total work or simply use leveling so that the
project spreads out sequentially. This is stupid, though - having to go
over every task in the project assigning a dummy resource to it. Not to
mention the fact that I have to make sure I skip all summary tasks on
the way, otherwise I get discrepancies.
Isn't there a report that just summarizes the amount of work involved
in the project, regardless of resources?
Thanks,
--itai