G
Gramps
How can I make the total time for a task not include time when there
are no subtasks. For example a task of developing a learning package
might contain 4 sub-tasks each of 6 days duration but the total task
time for development is given as 45 days because there are gaps between
the end of one sub task and the beginning of another.
are no subtasks. For example a task of developing a learning package
might contain 4 sub-tasks each of 6 days duration but the total task
time for development is given as 45 days because there are gaps between
the end of one sub task and the beginning of another.