A
Andreas Pfander
I have set up a number projects in Project Server.
One of the goals is to track how much time people actually spends on the
different tasks of the project. To make this reporting complete I would like
to also track the time that is spent on general tasks that are performed
outside a particular project. These may include "Administrative",
"Meetings", "Sustaining Engieering", etc.
I am aware, that resources can report non-working time (which I believe is
time not spent on the project), and that it is possible to transfer
non-working time from the Outlook calender into project to update the
project plan.
However, I am looking for a way so that people can enter their time spent on
these tasks in a timesheet view on a daily basis, so that I can later
analyze how much time was spent on each of these support functions.
Currently I have created a project with all the support tasks and have
assigned all resources to this project. I have entered an arbitrary duration
for the tasks. From what I can see this will mess up the availability of my
resources (they are now all assigned to this fictive project).
Is there any way to have people report time into certain categories while
not assigning them to these tasks and taking away from their availability?
Appreciate any help on this subject.
Thanks
Andreas
One of the goals is to track how much time people actually spends on the
different tasks of the project. To make this reporting complete I would like
to also track the time that is spent on general tasks that are performed
outside a particular project. These may include "Administrative",
"Meetings", "Sustaining Engieering", etc.
I am aware, that resources can report non-working time (which I believe is
time not spent on the project), and that it is possible to transfer
non-working time from the Outlook calender into project to update the
project plan.
However, I am looking for a way so that people can enter their time spent on
these tasks in a timesheet view on a daily basis, so that I can later
analyze how much time was spent on each of these support functions.
Currently I have created a project with all the support tasks and have
assigned all resources to this project. I have entered an arbitrary duration
for the tasks. From what I can see this will mess up the availability of my
resources (they are now all assigned to this fictive project).
Is there any way to have people report time into certain categories while
not assigning them to these tasks and taking away from their availability?
Appreciate any help on this subject.
Thanks
Andreas