H
Helge Svee
I'am trying to understand what Project 2003 does with the activities when
actuals are given.
What I have done:
Established 1 activity with duration = 20 days and work = 1000 hours, task
type = fixed duration. When I assign a resource to this activity I get
calculated that 6,25 units are needed. All this is no problem - and I save
the baseline for this project.
Then I tries to track actuals on this task. I use the dialog box "Update
tasks" and set the actual start to 2 days later than baseline start, the
actual finish to the same as baseline finish and % complete to 100%.
Project calculates work and actual work to 900 hours, but in my fictive
project actual work is 1000h, but i have used 2 days less than planned in the
baseline.
When I gives the value 1000h in actual work field I get an error message
from Project and Project "tells" me that the activity finished 2 days later
than I set in Update Task.
In online help - about task types it says that if i revise work for task
types fixed duration units are recalculated. This is not whats happens to me.
Therefor my questions are: "What have I done wrong ?" and "Do I have a wrong
setting in tools\options?"
actuals are given.
What I have done:
Established 1 activity with duration = 20 days and work = 1000 hours, task
type = fixed duration. When I assign a resource to this activity I get
calculated that 6,25 units are needed. All this is no problem - and I save
the baseline for this project.
Then I tries to track actuals on this task. I use the dialog box "Update
tasks" and set the actual start to 2 days later than baseline start, the
actual finish to the same as baseline finish and % complete to 100%.
Project calculates work and actual work to 900 hours, but in my fictive
project actual work is 1000h, but i have used 2 days less than planned in the
baseline.
When I gives the value 1000h in actual work field I get an error message
from Project and Project "tells" me that the activity finished 2 days later
than I set in Update Task.
In online help - about task types it says that if i revise work for task
types fixed duration units are recalculated. This is not whats happens to me.
Therefor my questions are: "What have I done wrong ?" and "Do I have a wrong
setting in tools\options?"