M
MSP Beginner
How come when I update actual finish and start dates on MSP2003, the Start
and Finish date only move along (not as in MSP2007, it is fixed).
For example, one task was planned with Start on 1-May and Finish on 30-May.
When updating progress, the task actually started on 5-May and finished on
3-June. But the original plan also moves from 1may-30may to 5may-3jun. How
should I do to keep the Start and Finish unchanged?
and Finish date only move along (not as in MSP2007, it is fixed).
For example, one task was planned with Start on 1-May and Finish on 30-May.
When updating progress, the task actually started on 5-May and finished on
3-June. But the original plan also moves from 1may-30may to 5may-3jun. How
should I do to keep the Start and Finish unchanged?