Tracking Question

C

Chris M

Can Project (or Project Server) be set up so that tasks
are tracked based on a percent complete rule base on 20/80
or 50/50, ie most the task is started it is 20% complete
and at the time of completion it is 80% complete?
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top