J
Justin Fults
I have a quick scenario I would like to throw out here.
I have multiple enterprise projects in which the teams
were built using the Enterprise Resource Pool. After
setting up my newest project plan and assigning each
resource to the appropriate tasks, I needed to level the
project to resolve an overallocation. After doing so,
the Project Finish Date has gone from mid-October to the
middle of February '04. After analyzing further, I found
that one specific resource was scheduled to complete a
task (which takes place early on in the Project) 2 months
later than the other tasks within the same Summary Task.
I looked at the availability of the resource during that
2 month time period and discovered that the resource
actually had no assignment work scheduled (other than
a .5 hour recurring task every Monday).
The Resource Calendar shows him as being available during
that time and everything else checks out? Why would
Project be delaying this task so far into the future when
the resource has the availability to complete the work?
My Level Settings are the default settings with the
exception of the "Leveling can create splits in remaining
work." value, which I have opted to "uncheck". Even
changing this back to its default value did not help.
Any suggestions? This seems like a unusual issue.
Thanks,
Justin
I have multiple enterprise projects in which the teams
were built using the Enterprise Resource Pool. After
setting up my newest project plan and assigning each
resource to the appropriate tasks, I needed to level the
project to resolve an overallocation. After doing so,
the Project Finish Date has gone from mid-October to the
middle of February '04. After analyzing further, I found
that one specific resource was scheduled to complete a
task (which takes place early on in the Project) 2 months
later than the other tasks within the same Summary Task.
I looked at the availability of the resource during that
2 month time period and discovered that the resource
actually had no assignment work scheduled (other than
a .5 hour recurring task every Monday).
The Resource Calendar shows him as being available during
that time and everything else checks out? Why would
Project be delaying this task so far into the future when
the resource has the availability to complete the work?
My Level Settings are the default settings with the
exception of the "Leveling can create splits in remaining
work." value, which I have opted to "uncheck". Even
changing this back to its default value did not help.
Any suggestions? This seems like a unusual issue.
Thanks,
Justin