B
bigfish3111
I was plugging in some resources to a project today and had never
noticed that on started or split tasks that the units does not change
once I start statusing.
For example: I create a 10 day activity that needs one person 100% of
the time. So my duration equals 10, work equals 80 hours, and units
equal 100%. Two days into the job I status the activity to say
they're on track by putting in 16 actual hours and 2 days actual
duration. Then I find out that the guy can only work the activity
half of the time but in the end will only need the original 80 hours
to complete the job. So I set the task to fixed work and stretch the
remaing duration out to 16 days. The units still say 100% even though
the remaing work is only scheduled for 4 hours a day.
Does the units recalculate once an activity has started?
Thanks,
Lou
noticed that on started or split tasks that the units does not change
once I start statusing.
For example: I create a 10 day activity that needs one person 100% of
the time. So my duration equals 10, work equals 80 hours, and units
equal 100%. Two days into the job I status the activity to say
they're on track by putting in 16 actual hours and 2 days actual
duration. Then I find out that the guy can only work the activity
half of the time but in the end will only need the original 80 hours
to complete the job. So I set the task to fixed work and stretch the
remaing duration out to 16 days. The units still say 100% even though
the remaing work is only scheduled for 4 hours a day.
Does the units recalculate once an activity has started?
Thanks,
Lou