M
Michael Carroll
Can someone assist me on this one?
I am trying to change the resource working time for multiple resources
however it appears as if this can only be accomplished one resource at a
time. The reason I ask for this is because I have a situation (quite common)
where I need to change the working time for a portion of the year from 7.5 hr
days to 9 hr days. I am also using a resource pool. In order for my schedule
to reflect the changes in hrs/day it appears as if I have to 1) update the
base calendar (simple) and 2) update the individual resource calendars.
Unfortunately, is appears as if MSP will not allow the user to update
multiple resource calendars at one time. Any input would be greatly
appreciated.
I am trying to change the resource working time for multiple resources
however it appears as if this can only be accomplished one resource at a
time. The reason I ask for this is because I have a situation (quite common)
where I need to change the working time for a portion of the year from 7.5 hr
days to 9 hr days. I am also using a resource pool. In order for my schedule
to reflect the changes in hrs/day it appears as if I have to 1) update the
base calendar (simple) and 2) update the individual resource calendars.
Unfortunately, is appears as if MSP will not allow the user to update
multiple resource calendars at one time. Any input would be greatly
appreciated.