In the Update Project dialog box I inadvertently input an incorrect date for
'Update work as complete through'. e.g. 10/12/06 instead of 10/10/06. This
then showed ALL of my tasks completed. When I try to input the correct date
i.e. 10/10/06 it still shows all tasks as completed.
How do I correct this?
'Update work as complete through'. e.g. 10/12/06 instead of 10/10/06. This
then showed ALL of my tasks completed. When I try to input the correct date
i.e. 10/10/06 it still shows all tasks as completed.
How do I correct this?