O
Ota Custes
Hi all,
I have two issues that I am sure are to do with setup.
The first issue is that of hours. If I set up a task that has 500hrs and
then assign two people to it, is there a way of automatically reducing the
time on the gantt chart to show 250hrs?
The second issue is to do with task splitting. I have another task which
requires a weeks work and then a break of three weeks. The remainder of the
work will be done after that but by someone different than that of the first
week. When I click and drag out a task for the second section of work, I get
a split dotted line and I cannot seem to be able to assign two different
people as described.
If someone can shed some light on how to overcome these problems or some
alternative practices / usages then I would be most greatful.
Thanks
I have two issues that I am sure are to do with setup.
The first issue is that of hours. If I set up a task that has 500hrs and
then assign two people to it, is there a way of automatically reducing the
time on the gantt chart to show 250hrs?
The second issue is to do with task splitting. I have another task which
requires a weeks work and then a break of three weeks. The remainder of the
work will be done after that but by someone different than that of the first
week. When I click and drag out a task for the second section of work, I get
a split dotted line and I cannot seem to be able to assign two different
people as described.
If someone can shed some light on how to overcome these problems or some
alternative practices / usages then I would be most greatful.
Thanks