S
sidd
Hi All
i am trying to use resource calendar to manage the vacation time for the resource
so i create a new enterprise calendar and assign it to enterprise resource
now,what i am not able to understand is where is the option in PWA to submit a vacation request t
manger when using resource calendar
for example if i am using administrative project to acheive the same . i can log on as a team memebe
...clik on 'notify you manager time you will not be available for project' and then enter
proper hour in administrative task ....that generates a a task for manager approval
how do i do the same when using resource calendar
thank
siddhart
i am trying to use resource calendar to manage the vacation time for the resource
so i create a new enterprise calendar and assign it to enterprise resource
now,what i am not able to understand is where is the option in PWA to submit a vacation request t
manger when using resource calendar
for example if i am using administrative project to acheive the same . i can log on as a team memebe
...clik on 'notify you manager time you will not be available for project' and then enter
proper hour in administrative task ....that generates a a task for manager approval
how do i do the same when using resource calendar
thank
siddhart