N
norry
I’m working on a project which handles a multitude (about 200) of short tasks
(fixed duration) with an 8 h/day working calendar (8 a.m. to 5 p.m.)
I can resume my problem like this:
if a task can not be started and ended on the same day, it has to be delayed
to the next day.
Example:
Task A = 5 h (fixed duration)
Task B = 4 h (fixed duration)
Task B can not start on the same day of Task A because there is only 8 hours
working time. Task B will therefore start next day at 8 a.m.
Can somebody tell me how I can set a delay for Task B which is the result of
(working time) – (Task A duration)
only in the case that
(finish day of Task B) not equal (start day of Task B) ?
Thanks
(fixed duration) with an 8 h/day working calendar (8 a.m. to 5 p.m.)
I can resume my problem like this:
if a task can not be started and ended on the same day, it has to be delayed
to the next day.
Example:
Task A = 5 h (fixed duration)
Task B = 4 h (fixed duration)
Task B can not start on the same day of Task A because there is only 8 hours
working time. Task B will therefore start next day at 8 a.m.
Can somebody tell me how I can set a delay for Task B which is the result of
(working time) – (Task A duration)
only in the case that
(finish day of Task B) not equal (start day of Task B) ?
Thanks