Hi WSH,
To the best of my knowledge, no. The calendar view is a *Task* view. You
could split the screen and show the Resource Graph or Resource Usage View in
the bottom pane, but it will only show the availability for the resource
assigned to the task selected in the top pane (calendar). You can use the
Assign Resources dialog box, and click the Graph button to show Work,
Remaining Availability, or Assignment work for selected resources as well.
Hope this helps. Let us know how you get along.
Julie