S
Samantha
Hi,
I'm trying to use Ms Project as a Lead Time tool for purchasing. I'm a
novice and therefore, it might not be the best tool but was told to use it
anyway given the time constraint that we're under.
What I need to do is to compare the Start Date of the task with another date
(Change Order Date) that must be completed first before the Start Date. The
Change Order Date is not always necessary. But if it were required, I need
the project to let me know (eg. any time of alert or color change in task,
etc) that we will have a problem meeting the Start Date based on the
comparison with the Change Order Date.
For example, if
Start Date = 4/14/2008
ChangeOrderDate = 4/21/2008
Then, since ChangeOrderDate> StartDate, we will have a problem and we want
to be alerted.
Is this possible in MsProject? Any help is very much appreciated! Thanks in
advance!
I'm trying to use Ms Project as a Lead Time tool for purchasing. I'm a
novice and therefore, it might not be the best tool but was told to use it
anyway given the time constraint that we're under.
What I need to do is to compare the Start Date of the task with another date
(Change Order Date) that must be completed first before the Start Date. The
Change Order Date is not always necessary. But if it were required, I need
the project to let me know (eg. any time of alert or color change in task,
etc) that we will have a problem meeting the Start Date based on the
comparison with the Change Order Date.
For example, if
Start Date = 4/14/2008
ChangeOrderDate = 4/21/2008
Then, since ChangeOrderDate> StartDate, we will have a problem and we want
to be alerted.
Is this possible in MsProject? Any help is very much appreciated! Thanks in
advance!