Warning when have time in a task with an unfinished predecessor

S

susiew32

Is there a way to get a warning if you are giving actual start date or
duration to a task where the finish-to-start predecessor hasn't finished?

Thanks.
 
J

Jim Aksel

You'll need to wite a VBA Macro to do something like that.
In Rod Gil's book on VBA Programming for MS Project, he has code that will
list all predecessors to a task. As that loops through the predecessors, you
could modify the code to examine Actual Finish for those tasks and then set a
flag for you.

His book can be purchased at msprojectexperts.com

One of the other MVPs also has similar code out here in cyberspace, you may
want to try mousetrax.com
---
If this post was helpful, please consider rating it.

Jim

Visit http://project.mvps.org/ for FAQs and more information
about Microsoft Project
 
S

susiew32

Thanks for your quick response. That's a good idea. With al the checking
that Project does to make sure you don't mess up your plan, I would think
that would be one of them.
 