Week numbers in task calanedar

P

Perry

When I am entering a new task in the gant diagram I can click on the arrow on
"Start" or "End" to launch a calender in which I may choose start or end date.

Is there a way to display the week numbers in this calendar?
 
J

John

Perry said:
When I am entering a new task in the gant diagram I can click on the arrow on
"Start" or "End" to launch a calender in which I may choose start or end date.

Is there a way to display the week numbers in this calendar?

Perry,
The simple answer is "no". However, when setting up a schedule you
should NOT be directly entering dates for tasks. The only exception is a
task Start date may be entered if there are no valid predecessors for
that task and it does not start on the Project Start Date.

Task scheduling is why Project is used. That scheduling includes entry
of basic information by the user (i.e. Task Name, estimated duration,
and task links). Given that data Project then schedules the project.
Directly entering start and finish dates for tasks completely defeats
the reason for using Project.

John
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top