What is the difference between %Complete and %WorkComplete

R

Ryan

What is the difference between % Complete (column type) and % Work Complete?

If anyone can answer with moderate accuracy that would be great. Thanks!
 
J

JulieS

Hi Ryan,

From Help:

=========================================
Percent (%) Complete:
The % Complete fields contain the current status of a task, expressed as
the percentage of the task's duration that has been completed.

How calculated:
When a task is first created, the percent complete is zero percent. As
soon as you enter actual duration, remaining duration, or actual work
(which affects actual duration), Project calculates percent complete as
follows:

Percent Complete = (Actual Duration / Duration) * 100

Percent (%) Work Complete fields
The % Work Complete fields contain the current status of a task,
resource, or assignment, expressed as the percentage of work that has
been completed.

How Calculated When a task is first created, the percent work complete
is zero percent. If you enter actual work for the task, Project
calculates percent work complete as follows:

Percent Work Complete = (Actual Work / Work) * 100
===============================================

To get detailed help on the field in Project, insert the field into a
table view and click the hyperlink to go directly to help on that field.

I hope this helps. Let us know how you get along.

Julie
 