What is the difference between "Tracking ( table ) -> Phys % Comp" and "Earned Value ( table ) -> E

K

ks2008

"Physical % Complete: Also referred to as Earned Value % Complete, "

Here is my question.

What is the difference between "Tracking ( table ) -> Phys % Comp" an
"Earned Value ( table ) -> Earned value (EV)" ? I was expecting, the
should have the same value, but they are not , Why ?

Thanks
K
 
M

mukund.y

"Physical % Complete:    Also referred to as Earned Value % Complete,"

Here is my question.

What is the difference between "Tracking ( table ) -> Phys % Comp"  and
"Earned Value ( table ) -> Earned value (EV)" ? I was expecting, they
should have the same  value, but they are not , Why ?

Thanks
KS

--
ks2008
------------------------------------------------------------------------
ks2008's Profile:http://forums.techarena.in/members/106957.htm
View this thread:http://forums.techarena.in/microsoft-project/1259100.htm

http://forums.techarena.in

physical % complete is the what we enters physicaly, need to enter for
summary task also.. but in easrned value % for summary tasks it
calculates automativalyy...
 
J

JulieS

Hello KS,

If you hover your mouse over the column heading for any field, you
can click on the hyperlink for help for that field. I have never
heard Physical % complete referred to as Earned Value % complete.
Earned value is by default calculated on the % Complete field. You
can base EV on Physical % complete, but it requires changing some
settings.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 
A

Andrew Lavinsky

Think of EV as the dollar value of Physical % Complete:

EV = Phys % Complete X Baseline Cost

We use this so that we can roll up the tasks to a project level view of EV.
Otherwise we would have to weight all tasks equally, which is rarely the
case. To a certain extent, EV is the weighted rollup of Physical % Complete.
It's then translated into financial units to compare with the AC and PV
values.

If every task cost exactly $100 to implement, then your EV would equal Physical
% Complete.

-A


- Andrew Lavinsky
Blog: http://blogs.catapultsystems.com/epm
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top