Where are the Actuals?

B

Brad

Hi All,

I have a test project running in a PWA environment. I have a task that was
dated to start and finish on April 15th. I took a baseline snapshot of it.

I then posted actual work (through PWA) and completed it on April 17th. The
question is, why do my Actual Start and Actual Finish dates say April 15th
instead of April 17th?

Shouldn't the Actual Start and Finish reflect the actual date that the work
was applied?

Any help in understanding this would be helpful.

Thanks,
Brad
 
M

Mike Glen

Hi Brad,

Try posting on the server newsgroup. Please see FAQ Item: 24. Project
Newsgroups. FAQs, companion products and other useful Project information
can be seen at this web address: http://www.mvps.org/project/.

Mike Glen
Project MVP
 