Paul in Salt Lake City
I have created a project with all of my tasks and durations entered and
linked it to a master schedule. I then created a resource pool file and
linked the master schedule to the resource pool.
Since I'm doing all of the scheduling in the master schedule I clicked on
assign resources and there they were. As soon as I clicked on a task to
assign someone to ... there they went. So essentialy there are no resources
available to task.
I checked my resource sheet and all of my resources are listed at the top. I
verified my calenders and insured that all resources were available 100% of
the 7.5 hour work day (1/2 hr. off for clean up, etc.) So where are my
resources going when I try to select a task for them???
I am most confused, I am.
linked it to a master schedule. I then created a resource pool file and
linked the master schedule to the resource pool.
Since I'm doing all of the scheduling in the master schedule I clicked on
assign resources and there they were. As soon as I clicked on a task to
assign someone to ... there they went. So essentialy there are no resources
available to task.
I checked my resource sheet and all of my resources are listed at the top. I
verified my calenders and insured that all resources were available 100% of
the 7.5 hour work day (1/2 hr. off for clean up, etc.) So where are my
resources going when I try to select a task for them???
I am most confused, I am.