I have a task that takes 4 days, starting from Tuesday. However, the ending
day shown is Monday, why?
Milind
 
J

JulieS

Hi Milind,

Check the start time of the task. Go to Tools > Options, view tab and
select a date format that shows date and time. Chances are the task starts
later than the starting time of the working day and, as it takes 4 working
days, it ends after the starting time of the working day on Monday.

You may also want to view FAQ # 5 "Default Working Hours" at:
http://project.mvps.org/faqs.htm

Hope this helps. Let us know how you get along.

Julie
 