trevor said:
its a piplener project and im recreating it the way he did except one thing.
in his resource sheet he assigned resources for everytime he needed one.
for example 4 foreman would be forman 1, 2 etc., and i am using one and
applying 400% in the units
i just entered a duration, and assigned the same resources as he, just a
different way.
im not clear on actual hours either?
yes, i think so.
I still think that we need more detail. You say you entered a duration
and then assigned resources to the task. So is it the case that you
want that resource assigned at the default level? In what you have
described so far, you haven't described entering hours. If you enter
the hours that should be worked for each task by each resource, then
Project will correctly record that.
The finish date may well be different not only because of the hours but
also because of the way you have entered the resource essentially as a
single entity.
In order to get the amount of work right in your plan, split the window.
By clicking on each task in turn in the Gantt chart area, you can
adjust the amount of work assigned to each task in the lower pane. It
is probably best if you make each task to be of fixed work type. You
will probably also need to adjust the duration of tasks during this process.
After this, the amount of work in the plan will be correct.