RoadRawts
I set up a task on day 1 for either less than 8 hours of work or exactly 8
hours of work, the calendar work day, and Project ends the task on the next
calendar day. Why does it do that? It should start and end on the same day.
What am I doing wrong? I have tried Fixed Work, Fixed Duration, and Fixed
Units, but it doesn't seem to make much difference.