Why does calender view show task bar as a line?

M

Maria

I am trying to get my tasks on the calender view, but some of them are shown
as a long line and if there is a second task on the same day, it shows up on
an extra page. Please help!
 
M

Mike Glen

Hi Maria,

Welcome to this Microsoft Project newsgroup :)

The long line is prbably a summary task. If you don't want them, then set
them as blank via Format/Bar Stlyes...

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 