C
Chris - FidelityFlight
I have a task that is 15 days in duration. The task is 8 days complete and
has a remaining duration of 7 days. The task started on Aug 26.
When I update the task with the actual start of Aug 26 and an actual
duration of 8 days, Project calculates the remaining duration of 7 days.
That is good. However, it pushes the finish date to Sept 23rd. That would
make the duration to be 20 days.
I tried something else to see what would happen. I updated the task to show
an actual start of Aug 26 and an actual finish of Sept 16. That should be a
15 day duration. However, Project calculates it to be only a 10 day
duration.
The task is not constrained by any parameters, and has only one predecessor
and one successor that are simple FS relationships. The task is not critical
either.
What is going wrong? I want the durations to reflect a real number so I can
use the info for historical data. This isn't the first time I have had this
happen either.
has a remaining duration of 7 days. The task started on Aug 26.
When I update the task with the actual start of Aug 26 and an actual
duration of 8 days, Project calculates the remaining duration of 7 days.
That is good. However, it pushes the finish date to Sept 23rd. That would
make the duration to be 20 days.
I tried something else to see what would happen. I updated the task to show
an actual start of Aug 26 and an actual finish of Sept 16. That should be a
15 day duration. However, Project calculates it to be only a 10 day
duration.
The task is not constrained by any parameters, and has only one predecessor
and one successor that are simple FS relationships. The task is not critical
either.
What is going wrong? I want the durations to reflect a real number so I can
use the info for historical data. This isn't the first time I have had this
happen either.