S
Scott71384
OK, I am trying to update my schedule and when I enter a percent completion
for any of the tasks, MP makes it a split task. Only when I enter 100%
complete, MP leaves the task as it was.
So this is what I am basically doing, I am a general contractor trying to
update my schedule. I sub-out all of my work (tasks) to subcontractors and I
assign each of these subcontractors to my tasks as "fixed contract fees". I
followed my “MP help book†to assign these tasks but I have this gut feeling
that may be the problem. I believe that is the problem because the book
tells you to enter 0 in the unit’s column on the task form and make it a
fixed duration. I would ABSOLUTELY appreciate it if anyone could solve this
dilemma for me; I have read all I possibly could out of the “MP help bookâ€
and have gotten nowhere. I am sure my question is not very clear, so if
anyone has a problem with my question, post it, and I will be happy to clear
it up for you.
Thanks, Scott
for any of the tasks, MP makes it a split task. Only when I enter 100%
complete, MP leaves the task as it was.
So this is what I am basically doing, I am a general contractor trying to
update my schedule. I sub-out all of my work (tasks) to subcontractors and I
assign each of these subcontractors to my tasks as "fixed contract fees". I
followed my “MP help book†to assign these tasks but I have this gut feeling
that may be the problem. I believe that is the problem because the book
tells you to enter 0 in the unit’s column on the task form and make it a
fixed duration. I would ABSOLUTELY appreciate it if anyone could solve this
dilemma for me; I have read all I possibly could out of the “MP help bookâ€
and have gotten nowhere. I am sure my question is not very clear, so if
anyone has a problem with my question, post it, and I will be happy to clear
it up for you.
Thanks, Scott