Why levelling move start date ?

D

daniariete2000

Hello !
My problem is :
I have 5 consolidated projects with just a resource allocated to them.
There are several overallocations and when I try to use levelling
there is a gap at the beginning of first task in first project. In
other words..the start date of first project is transslated without
any reasons.
Anyone can help me ?

Thanks

Daniele
 
M

Mike Glen

Hi Daniele,

Welcome to this Microsoft Project newsgroup :)

Check any calendars you have in Tools/Change Working Hours. Make sure you
have no summaries with the resource assigned. Try levelling to a different
granularity like hour by hour. I can't think of anything else - post back.

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :))

Mike Glen
MS Project MVP
 
D

davegb

Maybe you have a resource unavailable until after the start date of the project.

David G. Bellamy
Bellamy Consulting
 