C
Charles
Since everyone has been so helpful, I thought I'd post
another question that has us stumped.
We have a project plan in which we have a number of tasks
that have a certain duration, generally a day, that need
to be completed within a certain time frame, generally a
particular week. In order to properly track these tasks,
should we make these tasks "Fixed Work" so that we can
enter a duration of 1 day but be able to enter Start and
Finish dates that reflect the week in which the task must
be completed?
As an example, we have a task that must be completed
sometime during the week of 09/28 - 10/04, but will only
require 1 day of effort.
Any assistance would be greatly appreciated.
Thanks again,
Charles
another question that has us stumped.
We have a project plan in which we have a number of tasks
that have a certain duration, generally a day, that need
to be completed within a certain time frame, generally a
particular week. In order to properly track these tasks,
should we make these tasks "Fixed Work" so that we can
enter a duration of 1 day but be able to enter Start and
Finish dates that reflect the week in which the task must
be completed?
As an example, we have a task that must be completed
sometime during the week of 09/28 - 10/04, but will only
require 1 day of effort.
Any assistance would be greatly appreciated.
Thanks again,
Charles