M
Markarina
using Microsoft project 2007 is there any way to see if an individual
resources working hours has been changed from standard for example, if
I change a resources working hours from being 8:00 till 12:00 and
13:00 till 17:00 to being 8:00 till 12;00 there is no obvious way to
see that this has been done from looking at the resource sheet.
it also seems to be another idiosyncrasy of Microsoft project that
although it recognizes that if the resource can only work half a day
that a one day of work task will take two days to complete however if
a resource is available to work 16 hours a day (yes I know it's not
legal) it does not recognize the fact that a 16 hour work task can be
completed within one day without the resource been shown as over
allocated
resources working hours has been changed from standard for example, if
I change a resources working hours from being 8:00 till 12:00 and
13:00 till 17:00 to being 8:00 till 12;00 there is no obvious way to
see that this has been done from looking at the resource sheet.
it also seems to be another idiosyncrasy of Microsoft project that
although it recognizes that if the resource can only work half a day
that a one day of work task will take two days to complete however if
a resource is available to work 16 hours a day (yes I know it's not
legal) it does not recognize the fact that a 16 hour work task can be
completed within one day without the resource been shown as over
allocated