Paul --
If I understand the issue correctly, you want to set every Friday as a
non-working day for one particular resource, right? If so, here's how:
1. Apply the Resource Sheet view and double-click the name of the resource
in question.
2. Click the Change Working Time button.
3. In the Change Working Time dialog, select the Work Weeks tab
4. Click the Details button
5. In the Details dialog, select Friday
6. Select the "Set days to nonworking time" option and click OK.
7. Click OK to close the Change Working Time dialog.
8. Click OK to close the Resource Information dialog.
9. Save your project.
Hope this helps.
Paul Goldmann said:
Hi Dale,
Yes, I know. But in previous versions I could select the row header for
example for Friday and set this as free, BUT now I have to enter a start
and end date for the calendar exception and I do not want to limit the
exception to dedicated time period.
Thanks again
Paul