R
rkilgore
Start a blank project and set Project Calendar 24 Hour. The Gantt chart does
not change the display of non-working time and the default start time for the
first activity is stil 8:00 AM. ????? It appears the calendar has actually
changed because task duration does exceed 5:00 PM and can be started at hour
0, but why does the non-working time still appear on the Gannt chart?
And if it is a bug, how does it get reported?
not change the display of non-working time and the default start time for the
first activity is stil 8:00 AM. ????? It appears the calendar has actually
changed because task duration does exceed 5:00 PM and can be started at hour
0, but why does the non-working time still appear on the Gannt chart?
And if it is a bug, how does it get reported?