Add Main Task to Resource Usage View?

T

tommcbrny

Hello,

Is there a way to include the main task to the Resource Usage view in Project?

I need to do manual contouring to split resources among simultaneous tasks.
The resource usage view shows only the subtask name and not the main task
with which it is associated. Many sub tasks in my project have the same name
(development, testing, rollout, etc), and I'd like to see the main task to
keep things straight if possible.

Thanks,

Tom
 
J

JulieS

Hi Tom,

Sorry, the Resource Usage view doesn't show summary tasks. However, you
can add the Task Summary Name field to the table (left side) of the view
to see the assignment's summary task.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top