J
JZ
There is a task has to be done with in a fixed time. When I created the task,
the duration is 2 weeks. However once I assign two people to it, it will
prolong to 4 weeks. How can I make it show as 2 weeks on the Gantt chart?
And also sometimes after I created a task, somehow a constraint such as "No
earlier than" was generated and I have trouble to remove it. I changed it to
"ASAP" but it managed to changed back by itself. How could that happen?
the duration is 2 weeks. However once I assign two people to it, it will
prolong to 4 weeks. How can I make it show as 2 weeks on the Gantt chart?
And also sometimes after I created a task, somehow a constraint such as "No
earlier than" was generated and I have trouble to remove it. I changed it to
"ASAP" but it managed to changed back by itself. How could that happen?