Adding Resources to an existing task

J

JudyP

How can I add a resource (people) and assign their time to an existing task
without the formulas updating and changing the time allocation for all the
other resources I've entered in the task already?
 
J

Jan De Messemaeker

Hi,

Select the task, double-click, in Task Information, Advanced, check OUT
effort-driven.
HTH
 