G
Guy Montgomery
Hi,
I have a PERT chart with some milestones which have SF
links with negative lag from tasks that succeed them. I am
doing this to indicate that as the tasks are delayed, the
delivery milestones can slip. What I had hoped was that on
the PERT chart the arrows would point fom the start of the
task box to the end of the milestone box. Instead they come
from the end of the task box to the start of the milestone
box, which looks odd, as it seems to imply the milestone is
a successor to the task, not the other way round. Is there
a way to make the arrows do what I want,
Thanks,
Guy Montgomery.
I have a PERT chart with some milestones which have SF
links with negative lag from tasks that succeed them. I am
doing this to indicate that as the tasks are delayed, the
delivery milestones can slip. What I had hoped was that on
the PERT chart the arrows would point fom the start of the
task box to the end of the milestone box. Instead they come
from the end of the task box to the start of the milestone
box, which looks odd, as it seems to imply the milestone is
a successor to the task, not the other way round. Is there
a way to make the arrows do what I want,
Thanks,
Guy Montgomery.