Assigning a resource

M

m4u2nv

Is there a way of assigning a resource to a task but it not appearing
in there timesheet but still booking their time so that no other
Project Manager can double book?

So a PM can request the resources but the Resource Planner gets to
decided what resources are assigned.

Thanks.
 
D

Dale Howard [MVP]

m4u2nv --

Why don't you use Generic resources for this purpose? This allows the
Resource Planner to see what type of resource is needed on each task and
then to select the appropriate human resources. Hope this helps.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top