Assignments from Resource Pool

J

johnPMP

I'm using a resource pool. When I try to assign resources to a task using
the resource assignment dialog box each resource's name is displayed four
times. Though each resource's name only displays once in the pool and I do
not have resources in the sharer file. I use MS Project 2003.
 
J

Jan De Messemaeker

Hi,

This sounds as if your sharer files are not connected to the pool.
In the pool, Tools, Resource Sharing, Share resources: do you se the
addresses of the sharer files?

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 