S
sender
I am new to project, and have a basic question.
Lets say I have 3 tasks:
T1 - 10hrs - assigned to Person1
T2 - 8hrs - assigned to Person1
T3 - 16hrs - assigned to Person1
once this is entered into project, is there a way to auto schedule out the
gantt chart.
so that no more than 8 hrs is scheduled for Person1 on any day.
In other words, auto move the tasks so that T1 is first then T2, then T3?
thanks in advance
Lets say I have 3 tasks:
T1 - 10hrs - assigned to Person1
T2 - 8hrs - assigned to Person1
T3 - 16hrs - assigned to Person1
once this is entered into project, is there a way to auto schedule out the
gantt chart.
so that no more than 8 hrs is scheduled for Person1 on any day.
In other words, auto move the tasks so that T1 is first then T2, then T3?
thanks in advance