J
jjackson3755
I’m trying to update our schedules to reflect actual start dates an
progress with separate activity lines so that the baseline schedul
doesn’t change. It seems that however I try to do this the baselin
schedule adjusts to the actual start date; e.g., the baseline start dat
for the X-ray / CT Scan pre-construction was set for July 1, 2009 bu
this didn’t take place until July 16, 2009. When I try to insert th
actual start date in the schedule the entire baseline schedule change
to match the actual start date so you can’t really track the actua
dates compared to the baseline dates.
What am I doing wrong
progress with separate activity lines so that the baseline schedul
doesn’t change. It seems that however I try to do this the baselin
schedule adjusts to the actual start date; e.g., the baseline start dat
for the X-ray / CT Scan pre-construction was set for July 1, 2009 bu
this didn’t take place until July 16, 2009. When I try to insert th
actual start date in the schedule the entire baseline schedule change
to match the actual start date so you can’t really track the actua
dates compared to the baseline dates.
What am I doing wrong