N
Nik003
This is really weird,
Baseline work shows a certain value in the default project details view, but
it shows a different value in a custom view. It's almost like the values for
the custom views are pulled from a different place.
Also, when baselining a project, baselines are at the task level only? there
is no more general project baseline? Issu is a s follows: project is
initially baselined, later on other tasks are added to the project, so now
the project shows as not baselined, and when you look at the tasks, the
original ones are baselined, the new ones are not... but overall indicator
for the project should be baselined, because that's what it started with, all
the new tasks are changes, and should not affect the initial baseline.
Any help much appreciated.
Baseline work shows a certain value in the default project details view, but
it shows a different value in a custom view. It's almost like the values for
the custom views are pulled from a different place.
Also, when baselining a project, baselines are at the task level only? there
is no more general project baseline? Issu is a s follows: project is
initially baselined, later on other tasks are added to the project, so now
the project shows as not baselined, and when you look at the tasks, the
original ones are baselined, the new ones are not... but overall indicator
for the project should be baselined, because that's what it started with, all
the new tasks are changes, and should not affect the initial baseline.
Any help much appreciated.