Robert Watson-Hemphill
Hello. Looking for some advice on what I've done that keeps BCWP from equaling BCWS when a task is 100% complete and status date equals task finish date. BCWP is currently 75% of BCWS, and if I advance my status date 18 days past the finish date of the task, the numbers equal.
For reference, I have a non-effort driven, fixed duration task that is 100% complete (%complete and %work complete equals 100), the baseline and actual durations are equal, remaining work equal zero, and baseline and actual start and finish dates equal.
Does anyone have suggestions? Thanks in advance for any help
For reference, I have a non-effort driven, fixed duration task that is 100% complete (%complete and %work complete equals 100), the baseline and actual durations are equal, remaining work equal zero, and baseline and actual start and finish dates equal.
Does anyone have suggestions? Thanks in advance for any help