When I produce an EV report for all task (no summary task
option selected) I get one value for BCWS. Then making no
changes to the plan (e.g., status date, current date,
etc.) and print another EV report this time looking at
selected summary tasks, including the summary task for the
entire project BCWS shows a significantly different
value. Other values on the report (e.g., BCWP, and ACWP)
are identical between the two reports. Any ideas on what
might be happening?