J
John Mac
Hi-
I have entered a one week vacation using the resource sheet/set non
working time.
The Gantt view did not move scheduled work for those dates out until
the resource's return.
Tools/tracking/update project had no effect...
A basic function...have no idea what I'm doing wrong.
Also, is there a way to show non-working time of resources in the time
scale view? There is a tab, but can't get it to show color changes
anywhere.
Thanks
I have entered a one week vacation using the resource sheet/set non
working time.
The Gantt view did not move scheduled work for those dates out until
the resource's return.
Tools/tracking/update project had no effect...
A basic function...have no idea what I'm doing wrong.
Also, is there a way to show non-working time of resources in the time
scale view? There is a tab, but can't get it to show color changes
anywhere.
Thanks